Comments on Draft submitted to MDE

 

You will need Adobe Acrobat to read the documents - go here to get a copy

 

gpd = gallons per day.

Comparison Table:

  1st Draft 2nd Draft Draft to MDE Notes
Baseline Average Flow 373,500 gpd 340,000 gpd 340,000 gpd  
Remaining Flow 127,000 gpd 160,000 gpd 160,000 gpd  
- Flow due to outstanding permits 30,500 gpd 12,500 gpd 12,500 gpd = 72 units connected since 1st draft
= Available Flow 96,500 gpd 147,500 gpd 147,500 gpd  
- Wet Weather Reserve 16,500 gpd (3.3%) 20,000 gpd (4%) 20,000 gpd (4%) % of total plant capacity (500,000 gpd)
         
/2 = Available 1st Year 40,000 gpd 63,750 gpd 63,750 gpd  
Institutional 2,000 gpd (5%) 2,000 gpd (3.1%) 2,000 gpd (3.1%) 1,250 already committed for Hospice Facility
Commercial/Industrial 8,000 gpd (20%) 15,000 gpd (23.5%) 23,750 gpd (37.3%) 5,270 already committed first year
Residential Infill 1,000 gpd (2.5%) 5,500 gpd (8.6%) 5,500 gpd (8.6%)  
Other developments 3,000 gpd (7.5%) included as infill above included as infill above  
Northbrook/Symphony Village 26,000 gpd (65%) 41,250 gpd (64.7%) 32,500 gpd (51.0%)  

See Sec ID (Page 6): The plan still requires a new allocation even if the change in use results in fewer gpd of use.  This does nothing to encourage commercial development that results in lower usage.

See Sec IV (Page11): The plan names the Town Manager as the controlling authority and the Town Council as the approving authority for the first year of the plan.