Spill Photos

The 8/28/2004 Sewage Spill

 

You will need Adobe Acrobat to read the documents - go here to get a copy

 

Press Release from the Town 8/28/2004 - A 250 gallon spill works out to be about 1.5 minutes of pumping time at a station that pumps 240,000 gallons/day.

Photos from the spill on 8/28/2004 - right into a Chesapeake Bay drainage.

MDE Inspection Report from 8/13/2004 - "It was recommended by MDE inspectors to eliminate the flow meter column from the North Pumping Station Log Book at this time.